Germanys Energiewende - A Disaster In The Making
Fritz Vahrenholt
Germany
2017
Kalte Sonne
Fritz Vahrenholt, PhD Chemistry: In 2012, Germany decided to close its nuclear plants, which were concentrated in the south. It reshaped the grid, building huge DC cables from north to south. The wind is more abundant in the north. A total of 6100 km of cable will have to be built by the time the last nuclear power stations shut in 2022. 400 km have been given the go-ahead and 80 km have been built, just 1.3% of the total. Due to opposition to these cables, plans have been torn up. The government now plans to build them underground, increasing the cost eight fold.